Johnson Controls partnered with Infosys and TECEZE to execute a critical data center relocation from Milwaukee, Wisconsin, to Suwanee, Georgia. The project involved the secure decommissioning, transportation, and reinstallation of 50+ critical devices, with meticulous planning and execution achieving 100% SLA compliance and zero operational downtime.
Johnson Controls is a global leader in building management and systems, supporting complex operations that depend on reliable technology infrastructure. The relocation involved moving critical data center infrastructure between locations while maintaining operational continuity. With more than 50 devices involved, the project required precise coordination across decommissioning, transportation, installation, and testing.
Johnson Controls needed to relocate critical data center infrastructure from Milwaukee, Wisconsin, to Suwanee, Georgia, without affecting business operations. The project presented several distinct challenges that had to be solved together rather than in isolation. Logistical complexity meant sensitive IT equipment had to be safely transported across a significant distance while maintaining equipment integrity throughout transit. Technical complexity added another layer: devices needed to be carefully decommissioned, documented, transported, reinstalled, and tested without data loss or hardware damage, with no room for shortcuts at any stage of that sequence.
Operational continuity was non-negotiable — the relocation had to be executed without disrupting Johnson Controls’ critical services, meaning the move couldn’t simply pause operations for the duration of transit. And because every device and component required controlled handling throughout the move to ensure accurate reinstallation at the destination facility, precision execution had to be maintained consistently rather than only at the points considered highest-risk. Johnson Controls needed a delivery partner capable of managing a long-distance, multi-phase relocation with zero operational downtime and full device integrity from decommissioning through final reinstallation.
Infosys engaged TECEZE as its delivery partner to execute the data center relocation through a controlled, end-to-end process covering site assessment, decommissioning, logistics, installation, and testing. Both the source and destination data centers were thoroughly surveyed to assess site readiness, compatibility, and installation requirements before the relocation began, giving the team a clear picture of what each location required before any device was touched. Skilled technicians carefully decommissioned the critical devices and ensured each component was correctly catalogued and prepared for transportation, avoiding the ambiguity that can creep in when equipment moves without precise records. Specialised packaging materials and handling procedures protected the equipment during transit, with devices securely transported to the destination facility in Suwanee, Georgia over the distance from Milwaukee. Upon arrival, each device was methodically installed and tested against operational standards and SLA requirements to confirm functionality and readiness, and the relocation as a whole was managed as a structured transition, with planning and execution coordinated across the source and destination environments to minimise disruption throughout.
From challenge to transformation, the solution included:
Both source and destination data centers thoroughly surveyed to assess site readiness, compatibility, and installation requirements before relocation began.
Skilled technicians carefully decommissioning critical devices, with each component correctly catalogued and prepared for transportation.
Specialised packaging materials and handling procedures protecting equipment during transit, with secure transport to the Suwanee, Georgia facility.
Each device methodically installed and tested against operational standards and SLA requirements to confirm functionality and readiness.
“A project of this magnitude, moving our critical data center operations across states, was seamless. Infosys and TECEZE’s professionalism and precision ensured zero downtime and disruptions. We couldn’t have asked for a better partnership.”
— Senior Executive, Groupe CAT
Infosys served as the system integrator, partnering with TECEZE as the delivery partner for the critical data center relocation.TECEZE supported the execution across site survey, decommissioning, secure packaging and logistics, installation, and testing, ensuring that the infrastructure transition was completed with precision and minimal operational risk.
The successful relocation provides a proven model for organisations undertaking critical data center moves where uptime, equipment integrity, and execution accuracy are essential. TECEZE’s structured lift-and-shift approach enables organisations to transition critical infrastructure with greater control, from initial site readiness through final installation and operational validation.