Teceze delivered a compressed multi-region datacentre refresh programme as specialist delivery partner, successfully refreshing 11 sites across North America and Europe within a three-month window. The engagement covered site survey and the physical network device and server refresh at each location, achieving parallel dual-region execution of 100+ device replacements and validations while maintaining service continuity for infrastructure supporting connected health products.
A global health technology company producing diagnostic imaging, patient monitoring, and connected care systems, operating research, manufacturing, and commercial facilities across North America and Europe. Health technology organizations run datacentre infrastructure that supports both corporate operations and connected clinical products. Refresh activity must be sequenced with unusual care the systems being touched may sit in the service path for products deployed in hospitals. Infosys, as Systems Integrator, holds the client relationship and overall programme governance, and engaged Teceze as its specialist delivery partner for this dual-continent infrastructure modernization.
The client’s datacentre infrastructure supports both corporate operations and connected clinical products deployed in hospitals. Refresh activity must be sequenced with unusual care—the systems being touched sit in the service path for products that may be deployed in hospital environments. The programme required executing 11 site refreshes across North America and Europe within three months, replacing 100+ network devices and servers while maintaining service continuity for infrastructure supporting connected health systems.
Teceze implemented a structured refresh programme prioritizing pre-visit survey accuracy, parallel dual-region execution, and service continuity protection. The approach combined site survey preceding refresh activity at every location capturing rack layout, power, cabling, and dependency detail, parallel North American and European site execution under a single programme plan enabling 11-site completion in three months, combined network device and server refresh workstreams at each site halving change windows per location, and continuity-aware sequencing accounting for service dependencies to ensure infrastructure supporting connected health products was never left without a supported path during change. This model transformed a compressed multi-continent refresh into controlled, parallel execution with service continuity maintained throughout.
From challenge to transformation, the solution included:
A site survey preceded refresh activity at every location, capturing rack layout, power, cabling, and dependency detail so the refresh plan was built from verified conditions rather than existing documentation that was often incomplete or outdated, ensuring first-visit success.
North American and European sites were addressed in parallel under a single programme plan, making an 11-site refresh achievable within a three-month window through coordinated regional delivery teams.
Network device and server refresh were delivered together at each site rather than as separate visits, halving the number of change windows required per location and reducing aggregate site disruption.
Refresh sequencing accounted for service dependencies so infrastructure supporting connected health products was never left without a supported path during the change, protecting dependent clinical systems from interruption.
Operational transparency and stakeholder alignment are critical to program success. A layered governance model keeps refresh progress and service continuity visible across both regions:
| Cadence | Forum | Focus |
|---|---|---|
| Daily | Site Refresh Operations Review | Open change windows, site-level status, escalations |
| Weekly | Regional Progress Review | Refresh pace by region, dependency verification status, upcoming schedule |
| Monthly | Programme Governance Call | Overall completion rate, continuity incident review, schedule risk |
| Programme Close-Out | Final Governance Review | Full refresh completion across all 11 sites, SLA attainment, lessons learned |
“Executing an 11-site datacentre refresh across two continents in three months while protecting connected health systems is extraordinarily complex. Teceze’s survey-driven approach meant every site was planned precisely before we showed up. Parallel regional execution kept momentum going. Combining network and server refresh cut our change windows in half. Zero service disruptions to our connected products—that’s what matters. Their execution demonstrates they understand what happens downstream when health systems are involved. We’re now confident they can scale this approach as we modernize additional datacentres globally.”
– VP, Infrastructure & Operations, Health Technology Company
Teceze provides comprehensive datacentre refresh services including detailed site survey capturing rack layout, power distribution, cabling, and service dependencies at each location, parallel North American and European regional execution under unified programme management, combined network device and server refresh workstreams at each site, continuity-aware sequencing protecting dependent health systems from service interruption, expert equipment installation and configuration to validated standards, and complete validation and testing of all refreshed systems before sign-off.
The successful completion of this 11-site dual-continent refresh at accelerated pace while maintaining service continuity demonstrates Teceze’s capability to execute complex multi-region infrastructure modernization programmes for organizations with sensitive downstream dependencies. The survey-driven planning approach, parallel regional execution methodology, and continuity-aware sequencing framework established during this engagement create a reusable model for expanded datacentre modernization programmes. This engagement positions Teceze as a trusted strategic partner for the organization’s ongoing global infrastructure modernization.