Teceze delivered ongoing store dispatch services for a major US grocery retailer while simultaneously executing a 73-site UPS installation programme, maintaining full SLA on dispatch operations throughout the concurrent project with zero retail disruptions.
A major US grocery retailer requiring both ongoing store dispatch services and a large-scale 73-site UPS backup power installation programme. The organization needs consistent field dispatch while managing a significant infrastructure modernization initiative across the entire store footprint.
The grocery retailer required simultaneous execution of two major initiatives: maintaining perfect dispatch SLA supporting all store operations while executing a 73-site UPS backup power installation programme across the entire store footprint. Any dispatch failure during store operating hours directly impacts customer experience, while infrastructure installation creates operational complexity and potential disruption risk.
The engagement required: maintaining perfect dispatch SLA throughout installation programme, separating project and steady-state resources preventing core team impact, zero customer-facing disruptions despite concurrent infrastructure work, and completing installation on schedule without operational compromise.
Teceze implemented a parallel delivery model separating core dispatch from infrastructure project execution: maintained perfect dispatch operations as primary focus, dedicated independent resources for 73-site UPS installation preventing core team impact, installation scheduling coordinated to minimize store operational disruption, and comprehensive planning ensuring both initiatives succeeded simultaneously.
From challenge to transformation, the solution included:
Retail-focused dispatch procedures maintained throughout concurrent project ensuring core operations remained unaffected by installation programme.
Independent project resources separate from dispatch team ensuring installation programme did not draw on core team capacity.
Real-time visibility into both dispatch operations and installation progress enabling coordination preventing disruption.
Documented procedures ensuring rapid escalation and resolution preventing customer-facing disruptions during infrastructure work.
Governance structure focused on concurrent delivery oversight and disruption prevention:
| Cadence | Forum | Focus |
|---|---|---|
| Daily | Dual-Track Operations | Dispatch metrics, installation progress, disruption prevention |
| Weekly | Parallel Projects Review | Dispatch SLA, installation timeline, coordination status |
| Monthly | Concurrent Delivery Review | Dispatch metrics, installation progress, completion status |
| Quarterly | Business Review | Overall performance, project completion, strategic expansion |
“Teceze executed the UPS installation programme flawlessly while maintaining perfect dispatch. They kept the core team focused on store support while managing the installation independently. That kind of parallel delivery capability without disruption is exactly what we needed.”
— Retail Operations Director
Teceze delivered concurrent full-stack delivery: maintained dispatch operations with industry-specific protocols, deployed dedicated project team for UPS installation, coordinated both initiatives preventing disruption, and ensured both programmes succeeded simultaneously.
With 73-site UPS installation completed and dispatch operations maintained, focus shifts to leveraging modernized infrastructure and identifying additional strategic initiatives aligned with retailer growth.