Pharmaceutical company validates post-deployment wireless infrastructure across 43 APAC sites achieving 100% SLA within aggressive 8-week timeline
A diversified pharmaceutical and medical technology company with a growing presence across APAC (Asia-Pacific). The company recently deployed new manufacturing and research facilities across 6 countries and required rapid wireless infrastructure validation to support go-live schedules.
The organization faced aggressive go-live timelines for 43 new facilities across APAC while maintaining deployment momentum. Multi-country coordination across time zones added significant complexity, with survey work needing to happen in lockstep with operational readiness rather than as a separate, sequential phase.
Rapid validation was required without delaying operations, and findings had to integrate directly with operational readiness checklists. This also meant managing a clean handoff—training and knowledge transfer from survey teams to operations teams had to happen in real time, not as an afterthought once sites were already live.
Pharmaceutical companies expanding into APAC face aggressive go-live timelines where wireless infrastructure validation cannot delay facility opening or manufacturing commencement. Teceze’s approach to Pharma APAC’s post-deployment validation prioritized rapid validation methodology, multi-country team coordination, real-time issue identification and escalation, and seamless handoff to operations—delivering a model where wireless validation accelerates go-live rather than constraining it. Teceze implemented a rapid post-deployment validation strategy prioritizing speed and compliance: mobilized regional survey teams across APAC enabling parallel validation across time zones, deployed rapid validation cycles optimized for aggressive go-live timelines without quality compromise, implemented real-time issue identification and escalation ensuring no go-live delays, and managed seamless training handoff from survey teams to operations teams enabling independent ongoing management.
From challenge to transformation, the solution included:
Mobilized 8 regional survey teams coordinating validation cycles in parallel across time zones, enabling velocity impossible with sequential site-by-site validation while ensuring every site completed validation before go-live.
Developed rapid validation methodology capturing essential wireless infrastructure validation in compressed timelines, eliminating non-critical steps while maintaining regulatory compliance and safety validation.
Issues identified during validation were escalated and resolved immediately, preventing post-go-live complications—zero go-live delays across 43 sites demonstrates the effectiveness of this approach.
A comprehensive training programme enabled operations teams to assume wireless infrastructure responsibility upon go-live, with survey teams training them on infrastructure baseline, monitoring, and troubleshooting.
Operational transparency and stakeholder alignment are critical to program success. A layered governance model keeps program health and costs visible:
| Cadence | Activity | Participants |
|---|---|---|
| Daily | Site survey progress tracking | Teceze regional coordinator + site manager |
| Weekly | Regional status and escalation review | Teceze delivery manager + operations director |
| Bi-Weekly | Cross-country coordination | Teceze programme director + country leads |
| Weekly Executive | Go-live readiness updates | Pharma APAC executive leadership |
Post-deployment validation under aggressive timelines is a key success factor for regional expansion programmes. Achieving 100% SLA compliance across 43 sites in 8 weeks demonstrates the ability to maintain quality velocity while scaling operations.
“Coordinating 43 new site go-lives across APAC with an 8-week wireless validation window could have derailed the entire expansion. Teceze’s rapid deployment methodology kept us on schedule while maintaining zero go-live delays. That’s exactly what regional expansion requires.”
— Senior Operations Lead, AutoStore
Teceze mobilized 8 regional survey teams across APAC, coordinating rapid validation cycles across all 43 sites. Real-time issue identification and escalation ensured no go-live delays, while training transition from survey teams to operations ensured smooth handoff.
The expertise in rapid post-deployment validation, APAC expansion execution, and aggressive timeline delivery continues to drive value beyond initial go-live completion. The strategic partnership ensures sustained operational reliability, seamless future expansion capability, and continuous compliance monitoring aligned with growth strategy.